PS2003: Update Other Fields in Timesheet view.

In the Web Access Timesheet View (Accessed via the Tasks top navigation bar), team member by default can only update the % Work Complete and Remaining Work column.

It is quite often that people ask whether they can update other field. One of the common requests is for team member to update Actual Start date.

Here is how you do it...


http://workspaces.gotdotnet.com/jyps

Labels:

1 Comments:

At 6:29 AM, Anonymous Anonymous said...

Quite a few factual errors in your instructions: You can't save these settings in the Enterprise Global, so those steps add an element of risk that you're going to pollute it. Also, after you've added the field to both the published fields in the project, and the Project Web Access view (in this case the Timesheet), the user must republish the assignments to push the field to the timesheet.

 